Construction Report for July 1, 2019

Construction Project Report

 

 To be let:

 

FM-CO97(136)—55-97, D38 HMA resurfacing project between Bronson and the Moville Blacktop. Letting date: July 16, 2019.   Late start date: June 1, 2020.   The project involves cold in place recycling of existing pavement followed by an overlay of the pavement with new hot mix asphalt pavement.  

 

L-FM(D50)—7X-97, D50 Grading for Paving Project on 250th Street from Hwy 31 to County Route L27. Letting date: July 30, 2019.   Late start date: to be determined.   The project involves grading 250th Street for approximately 2.25 miles in preparation for paving. The project is funded by the $1.3 million special projects levy.

 

Under Contract:

L-B(C160)—73-97, County Bridge C160 is on Haskell Avenue between 140th Street and Iowa Hwy 141. Letting date: May 7, 2019. Late start date: September 3, 2019. Contractor: Graves Construction of Spencer, IA.   Contract price:    $620,679.27.  

This bridge was programmed for replacement in FY 2019. The existing bridge was destroyed in flooding during a June 2016 storm event. Contracts for the project have been approved by the Board of Supervisors.   Bridge construction is scheduled for the 2019 construction season.   The contractor has not yet announced a start date for the project.

 

FM-CO97(137)—55-97, K49 HMA resurfacing project between Plymouth County line and county route D12.  Letting date: February 19, 2019.   Late start date: to be determined. Contractor: Knife River.   Woodbury County share of contract price:   $286,297.37.  

This project is being done in coordination with a Plymouth County project on county route K49 in both counties.   The project involves cold in place recycling of the existing pavement followed by an overlay of high performance asphalt surfacing.   The high-performance surface provides a thinner overlay on top of the recycled pavement than standard hot mix asphalt.   This is Woodbury County’s first project using this material. Project work has started on the Plymouth County portion of the project.   Work is expected in the Woodbury County portion of the project in late August to earlySeptember.   Work in Woodbury County will be done under traffic control with a pilot car and flaggers maintaining traffic through the work zone.

 

L-B(U51)—73-97, 320th Street Bridge replacement.   Letting date: October 30, 2018.   Late start date: April 15, 2019.   Contractor: Graves Construction, Spencer, IA. Contract price: $475,343.66.   Working days: 65. This bridge has been closed since 2014 due to failed substructure piling.

The project allowed winter work at the contractor’s option and some work was completed. The contractor moved on site in January and removed the old bridge. Work on the project was delayed by spring flooding. The east abutment, east pier and west pier piling have been driven and all concrete work is done on those substructure elements. The west abutment piling are driven and the abutment will be poured Friday, June 28.   Falsework piling are in place and falsework construction is underway. We anticipate a bridge deck pour in 2-3 weeks. We expect the bridge to be done late summer/early fall 2019.

 

BROS-CO97(133)—55-97, Hancock Avenue Bridge replacement. Letting date: October 16, 2018 (IDOT Letting) Late start date: June 17, 2019.   Working days: 85.   Contractor: Dixon Construction.   Bid Price: $567,393.30. This project replaces an aging truss bridge on Hancock Avenue near the 200th Street intersection.  The project is funded with federal aid and farm to market funds. The current bridge is posted 3 tons.

            Dixon Construction has completed all channel work under the bridge and substructure is completed.   Bridge beams have been set and falsework construction is underway.   We are anticipating a late summer/early fall 2019 project completion.

 

BROS-CO97(132)—55-97, 150th Street Bridge replacement near Lawton. Letting date: June 19, 2018 (IDOT Letting). Late start date: May 1, 2019.   Working days: 105.   Contractor: Dixon Construction, Correctionville, IA. Contract price: $1,019,550.42.   This project replaced an aging bridge on 150th Street (Old Highway 20) north of Lawton.

Substantial work was completed during the winter and the deck was poured on Friday, April 5th.   All concrete work is done on the bridge.   Grading work is complete except for foreslope finishing, including seeding, mulching and fertilizing.   Paving at both ends of the bridge is complete. Shoulder construction is underway.   Guardrail is to be installed early next week. We expect the bridge to be open in about two weeks.

 

L-B(J9)—73-97, County Bridge J9 is on 170th Street between Jasper and Jewell Avenues. Letting date: August 21, 2018. Late start date: April 15, 2019. Contractor: Dixon Construction, Correctionville, IA. Contract price: $544,821.40. This bridge was one of the flood damaged structures from the June 18, 2016 storm event.   The bridge has been closed to traffic since it was damaged in the flood.

            Bridge construction is complete.   Approach roadway grading and guardrail berms need to be completed.   Guardrail installation and roadside seeding, fertilizing, and mulching remain.   We expect the bridge to reopen in about three weeks.

 

L-C(D156)—73-97, County Bridge D156 is on Franklin Avenue between 140th Street and 150th Street. Letting date: February 26, 2019. Late start date: July 8 2019. Contractor: Midwest Contracting, Marshall, MN. Contract price: $146,739.00. This bridge was programmed for replacement in FY 2019. The existing bridge was deteriorating and nearing the end of its service life.

            The contract has been signed by the board.   The contractor plans to move in around the middle of August.   The project should be complete by the end of September.

 

Work Under Design:

Design work is underway on the following projects for letting in 2019.

1)         The Mason Avenue bridge was severely damaged by flooding on the Little Sioux River in July 2018.   The bridge has been closed to traffic due to damage caused by the bridge being struck by a large tree.   The county engineer’s office was notified that FEMA has determined that the damage is eligible for repair/replacement assistance. The county road department has filed required documentation requesting assistance from FEMA with eligible costs and has started work on design of a new bridge at this location.   Preliminary design work is underway for a 209’ x 24’ continuous concrete slab bridge that meets the hydraulic requirements of this crossing.   There will still be road grade overflow on both sides of the bridge for extreme flooding, similar to the way the current truss has worked.   We will be submitting the design to FEMA shortly to obtain approval for an improved project.   We expect that work to be completed in 2020.             

 

2)         The county engineer is reviewing the cost to improve Benton Avenue south of 120th Street. The engineer will report estimated upgrade/improvement costs to the board ahead of their June 11, 2019 meeting.   Benton Avenue is a dead-end gravel road with several residences on either side of the road. For the second time in 10 years, the road suffered from severe instability during spring thaw. Options for improving the road to assure access are being explored by the Board and county engineer.