Construction Report for June 3, 2019

Construction Project Report

 

 To be let:

 

FM-CO97(136)—55-97, D38 HMA resurfacing project between Bronson and the Moville Blacktop. Letting date: July 16, 2019.   Late start date: June 1, 2020.   The project involves cold in place recycling of existing pavement followed by an overlay of the pavement with new hot mix asphalt pavement.  

 

 

Under Contract:

L-B(C160)—73-97, County Bridge C160 is on Haskell Avenue between 140th Street and Iowa Hwy 141. Letting date: May 7, 2019. Late start date: September 3, 2019. Contractor: Graves Construction of Spencer, IA.   Contract price:   $620,679.27.  

This bridge was programmed for replacement in FY 2019. The existing bridge was destroyed in flooding during a June 2016 storm event.   Letting was held May 7, 2019, the apparent low bid was awarded to Graves Construction on May 14, 2019. Contracts have been prepared, mailed to the contractor, and we are awaiting their return for board approval.   Bridge construction is scheduled for the 2019 construction season.

 

FM-CO97(137)—55-97, K49 HMA resurfacing project between Plymouth County line and county route D12.  Letting date: February 19, 2019.   Late start date: to be determined. Contractor: Knife River.   Woodbury County share of contract price:   $286,297.37.  

This project is being done in coordination with a Plymouth County project on county route K49 in both counties.   The project involves cold in place recycling of the existing pavement followed by an overlay of high performance asphalt surfacing.   The high-performance surface provides a thinner overlay on top of the recycled pavement than standard hot mix asphalt.   This is Woodbury County’s first project using this material. Work will be done in 2019.

 

L-B(U51)—73-97, 320th Street Bridge replacement.   Letting date: October 30, 2018.   Late start date: April 15, 2019.   Contractor: Graves Construction, Spencer, IA. Contract price: $475,343.66.   Working days: 65. This bridge has been closed since 2014 due to a failed substructure piling.

 The project allowed winter work at the contractor’s option and some work was completed. The contractor moved on site in January and removed the old bridge. Work on the project has been delayed by spring flooding. The road was under water for the three weeks during the recent floods.   East pier piling are driven and pile encasements are poured. East abutment piling are driven and the abutment has been poured.   Falsework piling have been driven on the east side of the ditch.   Work has shifted to the west side of the ditch.   We expect the bridge to be done late summer/early fall 2019.

 

BROS-CO97(133)—55-97, Hancock Avenue Bridge replacement. Letting date: October 16, 2018 (IDOT Letting) Late start date: June 17, 2019.   Working days: 85.   Contractor: Dixon Construction.   Bid Price: $567,393.30. This project replaces an aging truss bridge on Hancock Avenue near the 200th Street intersection. The current bridge is posted 3 tons.

            Dixon Construction has driven the south abutment piling and poured the abutment.   North abutment piling have also been driven and the abutment poured.   The contractor is awaiting delivery of the bridge beams.   We are anticipating a late summer/early fall 2019 project completion.

 

STP-S-CO97(134)—55-97, D50 PCC Resurfacing near Oto. Letting date: April 17, 2018.  Late start date: July 23, 2018.   Working days: 60. Contractor: Cedar Valley Corporation, Waterloo, IA. Contract price: $2,354,844.71.

            All work is complete.  

BROS-CO97(132)—55-97, 150th Street Bridge replacement near Lawton. Letting date: June 19, 2018 (IDOT Letting). Late start date: May 1, 2019.   Working days: 105.   Contractor: Dixon Construction, Correctionville, IA. Contract price: $1,019,550.42.   This project replaced an aging bridge on 150th Street (Old Highway 20) north of Lawton.

Substantial work was completed during the winter and the deck was poured on Friday, April 5th.   All concrete work is done on the bridge.   Grading work is complete and the approaches are staked for paving.  We are waiting for the paving subcontractor to move on site.   He has been delayed by weather.   We expect the bridge to be open early summer 2019.

 

L-B(J9)—73-97, County Bridge J9 is on 170th Street between Jasper and Jewell Avenues. Letting date: August 21, 2018. Late start date: April 15, 2019. Contractor: Dixon Construction, Correctionville, IA. Contract price: $544,821.40. This bridge was one of the flood damaged structures from the June 18, 2016 storm event.   The bridge has been closed to traffic since it was damaged in the flood.

            The bridge deck is poured and form material is being stripped. Bridge rail will be poured on Tuesday, June 4th.   Once the rail is poured, the bridge work is complete and the contractor will shape the approach roadway for guardrail installation.   We anticipate late June 2019 project completion.

 

L-C(D156)—73-97, County Bridge D156 is on Franklin Avenue between 140th Street and 150th Street. Letting date: February 26, 2019. Late start date: July 8 2019. Contractor: Midwest Contracting, Marshall, MN. Contract price: $146,739.00. This bridge was programmed for replacement in FY 2019. The existing bridge was deteriorating and nearing the end of its service life.

            The contract has been signed by the board.   My office is waiting to hear from the contractor with a proposed start date for the project.

 

Work Under Design:

 

Design work is underway on the following projects for letting in 2019.

1)         250th Street Grading Project - 2.25-mile grade for paving project south of Anthon.   Right of way will be necessary to allow construction of this road.   Final design is complete.  Plats for right of way acquisition are complete and acquisition has started. We completed right of way negotiations with landowners, but we are awaiting one signature on the agreement. We are working toward a July 2019 letting. This project is funded with the $1.3 million per year special project levy funds.

 

2)         The Mason Avenue bridge was severely damaged by flooding on the Little Sioux River in July 2018.   The bridge has been closed to traffic due to damage caused by the bridge being struck by a large tree.   The county engineer’s office was notified that FEMA has determined that the damage is eligible for repair/replacement assistance. The county road department has filed required documentation requesting assistance from FEMA with eligible costs and has started work on design of a new bridge at this location.   We expect that work to be completed in 2020 at this time.                     

 

 

3)         The county engineer is reviewing the cost to improve Benton Avenue south of 120th Street. The engineer will report estimated upgrade/improvement costs to the board ahead of their June 11, 2019 meeting.   Benton Avenue is a dead-end gravel road with several residences on either side of the road. For the second time in 10 years, the road suffered from severe instability during spring thaw. Options for improving the road to assure access are being explored by the Board and county engineer.